It’s our job to make sure that our 1.8 million customers have access to safe and reliable drinking water 24/7, 365 days of the year. But climate change and growing populations are putting increasing pressure on water resource availability in our area and across Southern England.
We’re continually planning, designing and innovating new, improved ways to make sure your water supply is resilient. So, to help address the growing supply risks affecting our Roadford supply area, we’re looking to invest in a new pumping station at Gatherley on the River Tamar and 4km of new pipework. Supported with a suitable abstraction license from the Environmental Agency, we’d use this new site to pump water from the river back into Roadford Lake during winter, when the river has a higher flow. These top-ups would help maintain the level of the reservoir so there’s less pressure on it and the river in the summertime when demand for water increases.
With the kind cooperation and generosity of landowners and local groups, our contractors and engineering, environmental and planning design teams are currently busy surveying the site to assess river flows, ecology and operational requirements.
The analysis also considers the wider impacts on the environment. These surveys will determine the design of the project, which is due to be finalised in 2023.
Why we’re doing this work:
We're submitting a new planning application at the end of September to install a set of temporary pumping equipment at the Gatherley site. This is so that we can bring forward the use of the pipe and enjoy the benefits of the scheme earlier than expected.
We hope to start taking water from the River Tamar and send it to Roadford Lake in February and March 2024 while the river has higher flows. As always, all abstractions will be undertaken according to strict licenses.
South West Water has been on site since October 2023 with the focus being on the new 4km cross-country pipeline which we plan to have installed by February 2024.
A temporary planning consent application has been made to setup plant and equipment to abstract water from the River Tamar at Gatherley during February - March 2024 and potentially the following winter, as required. A second temporary planning application has been submitted to cross the River Lyd with a pipe bridge to be used during February - March 2024, with the permanent below-ground pipeline crossing of the River Lyd to be made in summer 2024.
The purpose of the temporary planning applications and winter install of the cross-country pipeline is to enable water to be transferred to Roadford Lake this winter, to ensure we recover from the 2022 drought. Therefore, a time-limited 30 megalitre per day river abstraction licence application has been made to the Environment Agency following consultation with riparian and fishing stakeholders.
Looking beyond this winter, a permanent works planning application will be submitted in December 2023 to enable construction of a new 111 megalitre per day river abstraction and pump house to be constructed on the River Tamar at Gatherley from June 2024 to secure the region’s longer-term water resources. This permanent building has been designed to be in-keeping with the setting as far as possible and the river abstraction screens will be installed from the bank to minimise disturbance to the river bed. A new buried power supply will be installed alongside the 4km cross-country pipeline to power the pump house. We’ll be applying for the permanent 111 megalitre per day river winter abstraction licence from the Environment Agency in 2024 following approx. three years of consultation.
Works at Gatherley are expected to be completed by the summer 2025 for operational testing and use from November 2025. The winter operation of this site will be a strategic decision by South West Water and the water will directly benefit the region and will not be used for export outside of the South West Water region.
Further information on the need for the scheme and the water resources situation can be found in our draft Water Resources Management Plan 2025 – 2050
The following key dates are subject to relevant third party consents, permissions and approvals being in place:
In 2021, we launched our Green Recovery Initiative which focusses on opportunities for us to help the region economically and environmentally. So far, the Initiative has created work across the South West and has allowed us to make environmental contributions that go far beyond our 2020-25 business plan commitments. We also aim for a 10% net gain in biodiversity around our work sites to further enhance the environment in our region.
Roadford’s new intake pumping station is part of this Initiative. As well as increasing the resilience of the water supply, it is part of our long-term water quality strategy in the North Devon area.